Which of these is used when the process has achieved high capability level?

Thanh Thảo

New member
Which of these is used when the process has achieved high capability level?
A. Trial control limits
B. Actual control limits
C. Modified control limits
D. Easy control limits
 
Answer: c
Explanation: At the stage, when the process has achieved a high level of capability, there is some relaxation provided to the level of the surveillance provided. This is generally done with modified control limits in the case of x charts.
 