Calculate Takt Time when there are 500 minutes in work day and the customer demand is 500 units a day.
A. 1 minute
B. 2 minutes
C. 3 minutes
D. 4 minutes
Answer: a
Explanation: Takt Time = Net available work time / Customer demand, or, Takt time=500/500=1 minute. Takt Time is an important parameter measured in lean manufacturing.