Answer: b
Explanation: The floor and girders of through type structures should be placed in one continuous unless otherwise specified in which case a special sear anchorage should be provided to ensure monolithic action between the girders and floor and the case of tee beam slab floors, it is preferable to deposit concrete first up to the top of the girder ribs followed by concreting of the slab in one continuous operation and if the slab concrete is delayed, suitable shear keys should be formed by roughening the top of the girder before depositing the centre in the slab.