Ẽ Ẽm Thư New member Sep 19, 2021 #1 A discussion of uncertainty is critical for _____________ A. Characterization of risk B. Chemical analysis C. Pathway analysis D. Data calculation
A discussion of uncertainty is critical for _____________ A. Characterization of risk B. Chemical analysis C. Pathway analysis D. Data calculation
K Kim Trang New member Sep 19, 2021 #2 Answer: a Explanation: A discussion of uncertainty is critical to the full characterization of risk, because it provides a better understanding of the implications and limitations of the risk assessment (EPA 1991a). Upvote 0 Downvote