Which of the following scheduling test can be used to show that no scheduling exist?

Which of the following scheduling test can be used to show that no scheduling exist?
A. sufficient test
B. necessary test
C. complex test
D. simple test
 
Answer: b
Explanation: The necessary and sufficient conditions are used in the schedulability test. For necessary condition, the test is based only on the necessary conditions and it also can be used to show that no schedule exists. The sufficient condition indicates that no schedule exists even if there exists one.
 