Once a project is planned in terms of ‘events’ and ‘activities’ what next is important?

Once a project is planned in terms of ‘events’ and ‘activities’ what next is important?
A. Schedule
B. Activity
C. Time
D. Finishing
 
Answer: a
Explanation: Time required for completing each job has to be fixed with reference to attainable factors. A too short time or a too long time will prove unrealistic. Time duration has to be fixed with reference to experience, general availability of men and materials and completion of procedures.
 